Engineering construction | |||||
project name | Construction (Party A) unit | Construction address | Quality assessment | Construction safety record and completion time | Contract amount (ten thousand yuan) |
2×350mw2# unit construction and installation project of Chongqing Datang Shizhu Power Plant | Chongqing Electric Power Construction Corporation | Shizhu Tujia Autonomous County, Chongqing | A | Completion on schedule, no safety responsibility accident 2014.7.25 | 27496 |
Guodian Chongqing Hengtai Wansheng Power Plant 2×300mw Unit 1# Unit Construction and Installation Project | Chongqing Electric Power Construction Corporation | Chongqing Wansheng | A | Completion on schedule, no safety responsibility accident 2006.12.18 | 18923.168 |
Huaneng Power Plant Phase 3 2×600mw Unit 5# Unit Installation Project | Chongqing Electric Power Construction Corporation | Chongqing Jiangjin | A | Completion on schedule, no safety responsibility accident 2007.3.9 | 15787.256 |
Construction and installation of 2#300mw unit 1# unit of Chongqing Baihe Power Plant Phase II of China Power Investment Corporation | Chongqing Electric Power Construction Corporation | Kai County, Chongqing | A | Completion on schedule, no safety responsibility accident 2004.5.3 | 13262.4 |
Construction and installation of 2#300mw unit 2# unit of Chongqing Baihe Power Plant Phase II of China Power Investment Corporation | Chongqing Electric Power Construction Corporation | Kai County, Chongqing | A | Completion on schedule, no safety responsibility accident 2005.11.30 | 14103.56 |
Construction and installation of 1# unit of Datang Gangu Power Plant with large generation small 2×330mw technical upgrading project | Chongqing Electric Power Construction Corporation | Gangu County, Gansu Province | A | Completion on schedule, no safety responsibility accident 2007.9.30 | 12287.344 |
2×135mw unit main yard building and 1# unit installation project of CLP Yongchuan Power Plant Phase III Project | Chongqing Electric Power Construction Corporation | Chongqing Yongchuan | A | Completion on schedule, no safety responsibility accident 2007.11.15 | 9297.208 |
Huaneng Power Plant Phase II 2×300mw Unit Main Building Construction Project | Chongqing Electric Power Construction Corporation | Chongqing Jiangjin | A | Completion on schedule, no safety responsibility accident 1999.5.5 | 8000 |
Huadian Sichuan Guang'an Power Plant Phase I 2×300mw Unit 1# Unit Installation Project | Chongqing Electric Power Construction Corporation | Sichuan Guang'an | A | Completion on schedule, no safety responsibility accident 1999.5.5 | 10400 |
Guodian Dazhou Wanyuan Power Plant 2×300mw off-site construction pit power station main plant building and 1# unit installation project | Chongqing Electric Power Construction Corporation | Dazhou, Sichuan | A | Completion on schedule, no safety responsibility accident 2008.1.3 | 13328 |
Procurement and Construction of 220kV Nanhuabao Substation Project in Longxing Park | Chongqing Electric Power Construction Corporation | Liangjiang New District, Chongqing | A | Completion on schedule, no safety responsibility accident 2011.8.28 | 7524.3991 |
Nanning Pingli Vein Industrial Park- Domestic Waste Incineration Power Generation Project | Chongqing Electric Power Construction Corporation | Xingning District, Nanjing | A | Completion on schedule, no safety responsibility accident 2016.10.23 | 6500 |
Survey, deepening design and construction of the 110kV Baiyun Line No. 11 to No. 18 | Chongqing Electric Power Construction Corporation | Chongqing Liangjiang New District | A | Completion on schedule, no safety responsibility accident 2023.6.21 | 5797.7182 |
20mw photovoltaic project of Cailun Paper in Dayi County, Shaanxi Province | Dayi County Jiayi Energy Technology Co., Ltd. | Shaanxi Daxie | A | Completion on schedule, no safety responsibility accident 2023.8.30 | 5640 |
Xinduqiao~Ganggudi 500kV Line Project | Chongqing Electric Power Construction Corporation | Within the territory of Ganzi Prefecture, Sichuan Province | A | Completion on schedule, no safety responsibility accident 2013.12.20 | 5572.3762 |
Tajik Standan Gola Special Economic Zone 220/35/10 kV substation | Shaanxi Coal Chemical Central Asia Investment (Construction) Co., Ltd. | Tajikistan | A | Completion on schedule, no safety responsibility accident 2023.9.20 | 4266.2655 |
220kV transmission project of 500kV substation in Mingyue Mountain, northern Fujian | Chongqing Electric Power Construction Corporation | Chongqing Yubei | A | Completion on schedule, no safety responsibility accident 2011.5.30 | 4190.4558 |
110kV power transmission and transformation project of Huaiyuan River in Tongliang District, Chongqing | Chongqing Electric Power Construction Corporation | Tongliang District, Chongqing | A | Completion on schedule, no safety responsibility accident 2016.7.6 | 3309.6 |
110kV line project of Chongqing Jiangbei International Airport East Terminal Station and Third Runway Construction Project | Chongqing Electric Power Construction Corporation | Chongqing Jiangbei | A | Completion on schedule, no safety responsibility accident 2016.10.30 | 2435 |
Guangxi Binyang Mawang Wind Farm Project Delivery Line EPC General Contract | Chongqing Electric Power Construction Corporation | Binyang, Guangxi | A | Completion on schedule, no safety responsibility accident 2023.10.31 | 1744 |
Jiangjin Longjing 220 kV substation No. 3 main transformer expansion project | Chongqing Electric Power Construction Corporation | Chongqing Jiangjin | A | Completion on schedule, no safety responsibility accident 2014.12.30 | 1424.1372 |
Wuxi Mazhenba 110kv power transmission and transformation project | Chongqing Electric Power Construction Corporation | Wuxi County, Chongqing | A | Completion on schedule, no safety responsibility accident 2023.2.22 | 950.5412 |
Chongqing Jiulongpo Cap 110kV Transmission and Transformation Project | Chongqing Electric Power Construction Corporation | Chongqing Jiulongpo | A | Completion on schedule, no safety responsibility accident 2016.6.30 | 709.9463 |
No. 3 main transformer expansion project of 110kV substation in Huaxin Street, Jiangbei | Chongqing Electric Power Construction Corporation | Chongqing Jiangbei | A | Completion on schedule, no safety responsibility accident 2016.10.12 | 107.55 |
The first phase of electrical installation of the south bank of Yihe River in Luoyang Country Garden | Huaying City, Sichuan Province, South Sending and Transforming Co., Ltd. | LuoYang HeNan | A | Completion on schedule, no safety responsibility accident 2023.7.2 | 1108 |
Chongqing Electric Power Company Metrology Center Building Decoration Project (including environment and greening projects, etc.) | Chongqing Electric Power Construction Corporation | Chongqing Yubei | A | Completion on schedule, no safety responsibility accident 2008.6 | 41600 |
Chongqing Yunneng Shunchi Real Estate Asia Pacific City Phase I Project | Chongqing Electric Power Construction Corporation | Chongqing South Bank | A | Completion on schedule, no safety responsibility accident 2008.5 | 12800 |
Chongqing Yanneng International Real Estate s3, s4, s9 and other construction projects | Chongqing Electric Power Construction Corporation | Chongqing South Bank | A | Completion on schedule, no safety liability accidents 2008.3 | 9600 |
Chongqing Lianglu Square (Hilton Hotel Business Building) Project | Chongqing Electric Power Construction Corporation | Chongqing South Bank | A | Completion on schedule, no safety responsibility accident 1999.12.15 | 8444.8 |
Dingtai Apartment Building Project | Chongqing Electric Power Construction Corporation | Chongqing Yubei | A | Completion on schedule, no safety responsibility accidents 2005.3 | 3200 |
500kV Banan Substation New Construction Project | Chongqing Electric Power Construction Corporation | Chongqing Banan | A | Completion on schedule, no safety responsibility accident 2007.11.6 | 5222.4 |
Construction of the first section of the renovation project of Guanzhuang shantytown in Xinpu District, Zunyi City | Chongqing Electric Power Construction Corporation | Zunyi, Guizhou | A | Completion on schedule, no safety responsibility accident 2023.18.18 | 35727.42 |
Hongyuyuan Residential Quarter New Project Area a | Chongqing Electric Power Construction Corporation | Chongqing South Bank | A | Completion on schedule, no safety responsibility accident 2011.5.21 | 22864.8 |
Hongqiaoyuan residential community new project bcd district | Chongqing Electric Power Construction Corporation | Chongqing South Bank | A | Completion on schedule, no safety responsibility accident 2023.1.12 | 19428 |
Zunyi City Xinpu District Government Service Center Project | Chongqing Electric Power Construction Corporation | Zunyi, Guizhou | A | Completion on schedule, no safety responsibility accident 2023.9.27 | 16436.722 |
Chongqing Huamei·Lilyshan Project (Phase III, Section b) | Chongqing Electric Power Construction Corporation | A | Completion on schedule, no safety responsibility accident 2023.10.22 | 1258.6 | |
Equipment supply | |||||
project name | Construction (Party A) unit | product name | Supply quality | Product number | |
Chongqing Raffles City Project Residential Public Power Supply and Distribution System Project | Chongqing Chunan Power Technology Development Co., Ltd. | Low voltage distribution cabinet | excellent | GCS | 370.5135 |
Li'an Power Chongqing Rongchuangyang Coal Langyu Real Estate Special Post 2nd, 3rd and 5th Power Distribution Project | Chongqing Anchi Power Engineering Co., Ltd. | Low voltage distribution cabinet | excellent | GCS | 223.1755 |
Dagang Power Poly Golden Champagne High and Low Voltage Power Distribution and Household Watch Project (cf, g group) | Chongqing Anchi Power Engineering Co., Ltd. | Low voltage distribution cabinet | excellent | GCS | 134.5817 |
2023 second batch of agreement inventory cable tray and bridge cap goods procurement | Chongqing Fuling District Rui'an Electric Power Construction Engineering Co., Ltd. | Cable tray and bridge cap | excellent | National standard | 129.695 |